KEPM : Planning Framework
Steps & T-Codes to do planning in SAP CO
Display cost and activity input (KP07)
Display cost center/cost element planning in system by version and periodCopy plan to plan (KP97)
Copy planning data from period to period, from version to version.
Copy actual to plan (KP98)
Copy actual data to planning data from period to period, from actual data to any planning
version
Revaluate planning data (KSPU)
Revaluate planning data in period and version by percentage.
Delete planning data (KP90)
Delete cost element planning data in any version. It is required to control centrally.
Period lock (OKP1)
Use to lock planning version by period and by transaction
Change activity output/price (KP26)
Use to manual input or upload cost center/activity quantity planning by version and periodDisplay activity output/price (KP27)
Display cost center/activity quantity planning in system by version and period
Transfer Activity from PP (KSPP)
Transfer Schedule Activity quantity from SOP or MRP to planning version.
Plan Reconciliation (KPSI)
After run KSPP, we run KPSI to reconcile from Schedule Activity quantity to Plan Activity
quantity
Delete planning data (KP91)
Delete activity planning data in any version. It is required to control centrally
Change SKF planning (KP46)
Use to manual input or upload cost center/SKF planning by version and period
Display SKF planning (KP47)
Display cost center/SKF planning in system by version and period
Copy plan to plan (KP97)
Copy actual to plan (KP98)
Copy actual data to planning data from period to period, from actual data to any planning
version
Transfer SKF plan data from LIS (KVA4)
Transfer SKF plan data from LIS to planning version.
Delete planning data (KP91)