Hi,

Normally the flow will be like this if you are creating the asset through
settlement by using the transaction code CJ88 (Individual Settlement) or
CJ8G (Mass Settlements)

Order -> WBS -> AUC -> Asset

Since the error message says that WBS element budget exceed check the
budget/actual/variance for the respective project through transaction code
S_ALR_87013557 and check the allocation there if it exceed you need to get
back to the respective project contact to ask for budget supplement

Please check and let me know whether it resolves your query

Regards,
Ramakrishnan. S

---------------Original Message---------------
From: saisurendra Akkipeddi
Sent: Friday, July 08, 2011 4:59 AM
Subject: Availability Control

When i tried to Capitalise an asset from WBs

it is giving the message

item 003 wbs element budget exceeded

what to do in this, suggest me.

Thks in advance

__.____._
Copyright © 2011 Toolbox.com and message author.

Toolbox.com 4343 N. Scottsdale Road Suite 280, Scottsdale, AZ 85251
Mark as helpful
View this online
  
Popular White Papers

In the Spotlight
SAP Enterprise Mobility Webcast Watch today!
_.____.__

0 nhận xét:

Post a Comment

Blog Archive