I think you can change validity date through OKEON
| | | ---------------Original Message--------------- From: Uttam Maity Sent: Tuesday, August 09, 2011 5:42 AM Subject: Cost element 420010 does not exist You can extend the from date of the CE by creating it for the period it is missing. If you want to change the validity from date i.e. say from 01/04/2011 to 31.12.9999, then create the same CE in T.code KA01 for the period 01/04/2013 to 31/03/2099 by entering the same CE in both Cost element and Reference cost elements fields. After this then create the same CE in T.code KA01 for the period 01/04/2011 to 31/03/2013 by entering the same CE in both Cost element and Reference cost elements fields. With regards, Uttam Maity | | __.____._ Copyright © 2011 Toolbox.com and message author. Toolbox.com 4343 N. Scottsdale Road Suite 280, Scottsdale, AZ 85251 | | Popular White Papers In the Spotlight _.____.__ |