Hi Please check whether the budget you have released for the project is full or partial, and try to check the allotment given is utilised as per the budget given in the project at cj30
| | | ---------------Original Message--------------- From: saisurendra Akkipeddi Sent: Friday, July 08, 2011 4:59 AM Subject: Availability Control When i tried to Capitalise an asset from WBs it is giving the message item 003 wbs element budget exceeded what to do in this, suggest me. Thks in advance | | __.____._ Copyright © 2011 Toolbox.com and message author. Toolbox.com 4343 N. Scottsdale Road Suite 280, Scottsdale, AZ 85251 | | Popular White Papers In the Spotlight _.____.__ |