RE:[sap-acct] Unable to mark and release price

Posted by Vaani (Ms)
on Aug 1 at 12:17 AM
Please advise if my estimation in July 2011 & ck24 in August, whether the system would cause a problem.

---------------Original Message---------------
From: Vaani
Sent: Sunday, July 31, 2011 11:37 PM
Subject: Unable to mark and release price

Hi,

My user had done estimation on 31.7.2011 & try to mark & release price via CK24 but system say it is too late.

The system last day of the period is 31.7.2011.

We tried late price change but it still update the standard price & not planned price.

Please advice.